Kochi Metro Phase II further delayed: Commissioning pushed to Aug 2027
Kochi: Promised to be commissioned in Dec 2025, the ambitious Phase II project of Kochi Metro, connecting Jawaharlal Nehru (JLN) Stadium to Infopark via Kakkanad, will be delayed by over one-and-a-half years. Kochi Metro Rail Ltd (KMRL) officially said it aims to complete civil works by June 2027, with final testing, system integration and official commissioning rescheduled for Aug 2027.
A main reason for the delay in getting state govt’s approval for availing external funding to the tune of Rs 1,116 crore from AIIB (Asian Infrastructure Investment Bank).
“…the project financing process involved approvals from multiple agencies, and the sanction of external funding required for implementation took nearly one and a half years to materialise,” the agency said in a statement.
Furthermore, KMRL faced a roadblock when its proposal for Rs 7 crore to strengthen side roads used for traffic diversions was denied dedicated funding. It also faced severe utility hurdles that required multi-agency coordination and innovative design modifications.
“One of the most challenging stretches was the Civil Lane corridor between Pipeline Junction and Padamughal, where the presence of Indian Oil Adani Gas Pipeline impacted construction activities. Following its relocation by the agency concerned on Jan 1, 2026, piling and pier construction activities were taken up and completed,” it said.
Land acquisition also proved to be a major hurdle in JLN Stadium-Palarivattom stretch. Portions of required land were handed over in stages starting Dec 2024, with the final parcels cleared only in March 2026 due to ongoing court proceedings. This section also required the elaborate relocation of critical KWA water mains and KSEB high-voltage lines, including 220kV and 11kV networks.
Despite the hurdles, the 10.58-km elevated viaduct project achieved substantial physical progress within two years of awarding the major civil contract to AFCONS Infrastructure Limited in June 2024, a KMRL official said.
“Currently, all foundation piling and pile cap works for the 10 upcoming stations are complete. Additionally, 85% of viaduct piling is finished, and 3.5km of the superstructure is ready for track laying. Construction is moving at a steady pace of 25m to 30m per day, a rate expected to accelerate after the monsoon season,” the official said.
KMRL also finalized parallel system contracts for track work, power supply, signalling and telecommunications.
Meanwhile, ongoing construction works in JLN Stadium-Palarivattom stretch resulted in severe traffic jams, with only one-lane traffic possible in both directions.
“Weekly review meetings involving all concerned stakeholders are being conducted to assess progress and resolve issues on priority. During the monsoon period, reviews are being undertaken even more frequently to ensure uninterrupted progress and prompt rectification of field-level issues,” the official said.
“The authorities should promptly complete the crucial Pink Line, without any further delays as the same will lead to cost escalation,” said D Dhanuraj, Chairperson, Centre for Public Policy Research, a city-based social policy think tank.
“…the project financing process involved approvals from multiple agencies, and the sanction of external funding required for implementation took nearly one and a half years to materialise,” the agency said in a statement.
Furthermore, KMRL faced a roadblock when its proposal for Rs 7 crore to strengthen side roads used for traffic diversions was denied dedicated funding. It also faced severe utility hurdles that required multi-agency coordination and innovative design modifications.
“One of the most challenging stretches was the Civil Lane corridor between Pipeline Junction and Padamughal, where the presence of Indian Oil Adani Gas Pipeline impacted construction activities. Following its relocation by the agency concerned on Jan 1, 2026, piling and pier construction activities were taken up and completed,” it said.
Land acquisition also proved to be a major hurdle in JLN Stadium-Palarivattom stretch. Portions of required land were handed over in stages starting Dec 2024, with the final parcels cleared only in March 2026 due to ongoing court proceedings. This section also required the elaborate relocation of critical KWA water mains and KSEB high-voltage lines, including 220kV and 11kV networks.
Despite the hurdles, the 10.58-km elevated viaduct project achieved substantial physical progress within two years of awarding the major civil contract to AFCONS Infrastructure Limited in June 2024, a KMRL official said.
KMRL also finalized parallel system contracts for track work, power supply, signalling and telecommunications.
Meanwhile, ongoing construction works in JLN Stadium-Palarivattom stretch resulted in severe traffic jams, with only one-lane traffic possible in both directions.
“Weekly review meetings involving all concerned stakeholders are being conducted to assess progress and resolve issues on priority. During the monsoon period, reviews are being undertaken even more frequently to ensure uninterrupted progress and prompt rectification of field-level issues,” the official said.
“The authorities should promptly complete the crucial Pink Line, without any further delays as the same will lead to cost escalation,” said D Dhanuraj, Chairperson, Centre for Public Policy Research, a city-based social policy think tank.
You Can Also Check: Gold Rate in Kochi | Silver Rate in Kochi | Bank Holidays in Kochi | Public Holidays in Kochi
Comments
Be the first to share a thought and become theFirst Voiceof this News Article
end of article
In Kochi
- Bus crew saves toddler found sitting on busy road in Malappuram
- MGU lets off Maharaja’s principal after finding lapse in Arsho Promotion
- Man under observation for suspected Nipah infection
- Missing student’s body recovered from Malampuzha dam
- Police find no basis for action in actor’s complaint
- IMD issues orange alert for three districts on June 11
- Cashew Corp case: Comply with order by June 19, Kerala HC tells industries dept secy
Featured In City
- Bharathiraja, the man who could turn any woman into a star
- Accenture splits salary hikes between base pay, lump-sum payout
- Thief in police custody escapes from washroom window of Kamothe police stn, nabbed after 6 hrs
- CENTRE ALLOCATES RS 7.5K CR UNDER RURAL JOB SCHEME
- Devoid of basics, patients bear brunt at Kasturba Gandhi Hospital
- Will bring back state buses, trams: Arjun Singh
- Justice for R G Kar rape-murder, system reform on health minister’s prescription
Photostories
- You don't need a Gout attack to have high Uric Acid: The subtle symptoms doctors don't want you to ignore
- From Vinod Kambli to Virat Kohli; famous cricketers who own luxurious properties in Mumbai’s premium neighbourhoods
- From brightening creams to face serums: Why men’s skincare is finally having its moment in India
- All about ‘How to Train Your Dragon 2’ live-action cast: From Cate Blanchett to Mason Thames
- Sleeping enough but still tired? These vitamin deficiencies could explain why
- Mark Zuckerberg's $300 million superyacht Launchpad: Why everyone is talking about the 'big boat'
- Leaves turning chalky white: Here’s the reason behind it and how to fix it
- Forget the royals, Mahira Khan’s shimmering desi moment at King Charles’ charity dinner made her look like the main event and not a guest
- All about Knox and Vivienne: Angelina Jolie and Brad Pitt’s youngest 17-year-old twins
- 7 budget-friendly localities in Pune for rent in 2026: Affordable areas with strong connectivity
Videos
03:49 From Himanta To Bhupender: Are BJP Leaders Accelerating The TMC Rebellion?05:27 Pakistan Army Mi-17 Helicopter Crashes Near Muzaffarabad, All On Board Killed | Watch02:43 TMC Denies Congress Merger Buzz After Mamata-Sonia, Rahul-Abhishek Meetings | Watch03:51 AI-171 Victims' Families Question Claim Waivers Before Probe Ends; Air India Denies Pressure03:07 After Weeks In Captivity, 14 Freed In Manipur, Search Intensifies For Six Missing Men- Sushmita Dev Quits TMC & Rajya Sabha, Delivering Fresh Blow To Mamata Banerjee As TMC Crisis Deepens
- Paraquat Debate: Why Is India Still Allowing A Herbicide Banned In 74 Countries?
03:41 Narendra Modi Overtakes Jawaharlal Nehru As India's Longest-Serving Democratically Elected PM- POK Protests, Detentions & Killings Vs Zojila Tunnel: Two Very Different Stories Across Kashmir
Hot Picks
Top Trends
Up Next
Follow Us On Social Media