Your Privacy is Important to us

We encourage you to review our Terms of Service, and Privacy Policy.

By continuing, you agree to the Terms listed here. In case you want to opt out, please click "Do Not Sell or Share My Personal Information" link in the footer of this page.

Opt out of the sale or sharing of personal information

We won't sell or share your personal information to inform the ads you see. You may still see interest-based ads if your information is sold or shared by other companies or was sold or shared previously.

Continue on TOI App
Open App
Login for better experience!
Login Now
Welcome! to timesofindia.com
TOI INDTOI USTOI GCC
TOI+
  • Home
  • Live
  • TOI Games
  • Top Headlines
  • India
  • City News
  • Photos
  • Business
  • Real Estate
  • Entertainment
  • Movie Reviews
  • Lifestyle
  • Podcasts
  • Elections
  • Web Series
  • Sports
  • TV
  • Food
  • Travel
  • Events
  • World
  • Music
  • Astrology
  • Videos
  • Tech
  • Auto
  • Education
  • Log Out
Follow Us On
Open App
  • News
  • Videos
  • India
  • Elections
  • World
  • City
  • Tesseract
  • Life & Style
  • Entertainment
  • Business
  • Tech
  • TOI Games
  • Cricket
  • Sports
  • TV
  • Web Series
  • Education
  • Speaking Tree
  • Success Story of Visionary Leaders
  • TOI Newsletters
  • Health
  • Real Estate
  • Legal
  • Defence
  • Women

10 years on, Barapullah III still unfinished: 8.5-acre land dispute stalls key Delhi bridge project

Piyal Bhattacharjee
| TIMESOFINDIA.COM | Last updated on - Apr 8, 2026, 12:28 IST
Comments
Share
1/10

Planning failure: Work began without full land acquisition

The project’s biggest setback came from a basic lapse — construction started before acquiring all required land. Within a year, residents of Nangli Razapur objected, halting work on a crucial stretch and exposing gaps in initial planning.

2/10

Land dispute: 7-year delay over 8.5 acres

The dispute over around 8.5 acres of land dragged on from 2016 to 2023. Continuous back-and-forth between authorities and landowners stalled progress, leaving a 700-metre stretch and a key pillar incomplete for years.

3/10

Compensation deadlock: Rs 17 lakh vs Rs 3 crore per acre

The land, classified as riverine, had a notified rate of Rs 17 lakh per acre, while owners demanded Rs 3 crore. The disagreement led to prolonged negotiations, social impact assessments, and eventual settlement only in 2024.

4/10

Environmental oversight: Tree issue discovered late

Nearly a decade after project approval, officials identified about 300 trees along the alignment. This late discovery meant fresh surveys, compliance, and permissions, further delaying construction timelines.

5/10

Clearance delays: Legal and regulatory hurdles

Permissions under the Delhi Preservation of Trees Act and approvals from the Central Empowered Committee took time. Even after reassessment reduced tree cutting to 85, approvals for around 170 trees only came in July 2025.

6/10

Poor pre-execution surveys: Issues surfaced midway

Critical elements like high-tension lines, land conditions, and alignment challenges were not fully assessed beforehand. These had to be addressed during construction, leading to repeated interruptions and revisions.

7/10

Engineering complexity: Challenging floodplain construction

Building across the Yamuna floodplain required deep foundations of up to 50 metres and massive wells of 14 metres in diameter. Flooding risks and even a suspected pier tilt added to delays and technical difficulties.

8/10

Pandemic impact: Progress nearly stalled

The Covid-19 pandemic disrupted labour and logistics significantly. Between 2019-20 and 2022-23, progress barely moved from about 80% to 82%, highlighting the extent of slowdown.

9/10

Project opened in pieces

In August 2021, small sections were inaugurated despite the project being far from complete. This pattern of multiple inaugurations created a perception of progress without delivering full commuter benefits.

10/10

Cost overrun and hidden losses

The delay added an estimated Rs 400–600 crore to project costs. However, the real burden is far higher, including fuel wastage, pollution, lost productivity, and daily commuter stress due to prolonged congestion.

Top Comment
P
Pinaki
55 days ago
In plain english this is a "cluster***k" at the expense of tax payer's money.
Read allPost comment
Photostories
  • Kangana Ranaut skips fast fashion, embraces handloom royalty in Gaurang Shah’s majestic Kanjeevaram saree
  • Benefits of Tulsi Mala according to hindu traditions
  • 8 metro corridors driving residential growth and transforming India's urban housing landscape
  • Chaos, jumps, screams: Fire sweeps through Delhi's Malviya Nagar hotel, kills 21
  • Green anacondas can do THIS? 10 facts that may surprise you
  • Mumbai bullet train project: How 3rd tunnel breakthrough was achieved in just 5 months
  • Mrinal Tai Gore flyover extension set to change Mumbai's commute; what we know
  • Lalit Modi’s crores-worth London mansion is a 7,000 sq ft cricketing den with signed jerseys, lavish interiors and a private lift
  • Daily sacred rituals to enhance your Good Luck
  • Quote of the day by Marilyn Monroe: 'If you can make a woman laugh, you can make her do anything'
Explore more Stories
  • 10
    Chaos, jumps, screams: Fire sweeps through Delhi's Malviya Nagar hotel, kills 21
  • 8
    Mumbai bullet train project: How 3rd tunnel breakthrough was achieved in just 5 months
  • 8
    Mrinal Tai Gore flyover extension set to change Mumbai's commute; what we know
  • 8
    ​How Harbour Line western extension will change Mumbai’s rail connectivity
  • 9
    Annamalai plans secular-regional party with national outlook, redefined Dravidian vision
Up Next
  • News
  • /
  • City
  • /
  • Delhi
  • /
  • 10 years on, Barapullah III still unfinished: 8.5-acre land dispute stalls key Delhi bridge project